Tuesday, July 5, 2011

Vanity

Amanda earning her plumber's merit badge
Yesterday, we removed the toilet and the old vanity in preparation for installing the flooring in the powder room.  We had previously removed the vanity to remove the old linoleum floor, then re-installed it for the convenience of having a functional sink. 









It was a bit worse for wear, having endured the rain while sitting on the deck, and was on the verge of collapsing when we carried it out to the deck.









With the toilet out of the way, Sharron and Amanda removed the staples that had held the linoleum underlayment in place.












We added an extender ring for the toilet base flange to compensate for the increased height of the new flooring.







Sharron cut out a hole in the felt paper for the toilet.  I did something similar for the floor boards, but with a jig saw!













Marking end board for cutting






It took most of the day to get this small area covered with flooring, mainly due to working around the toilet base, but also in maintaining a good pattern with the board ends.  










Today I shimmed and installed the new vanity, and Amanda and I re-installed the toilet.  With plumber's putty around the bottom rim and a wax seal on the drain hole of the toilet, we had to avoid setting the toilet in the wrong spot.  With more than a little difficulty, we finally got the thing lined up with the floor flange mounting bolts and tightened down.  We installed the tank, connected the water line and gave it a thorough check for leaks.  None found!



Tonight, I leveled and secured the base cabinet to the left of the stove, after contacting our granite fabricator to discuss how much space to leave between the stove and cabinet.  The answer is 1/8 inch - just enough to pull the oven out for cleaning/maintenance.

Tomorrow I will wire the dishwasher and secure the second spice rack to complete the base cabinet installation work in the sink area.  Then, it is on to the island.  The granite fabricator is scheduled to come out on Monday to take measurements for the counter tops, and I hope to have the island cabinet work completed by Friday.

Sunday, July 3, 2011

Island Living

Today we installed the microwave shelf and assembled the second spice drawer and positioned the island cabinets in their approximate location.  Much work remains to get them secured to the floor, electrical outlets installed and wired, and the back panel installed. Sharron also sewed a very nice wall hanging that we installed to the right of the dining room cabinets.


Island from deck door


Island from dining room

Bird's eye view from dining room


Sharron's wall hanging by the dining room cabinets

Saturday, July 2, 2011

Venting

We started the day with a trip to Home Depot for some one-inch thick wood strips to install under the cabinet above the stove for the ventilation fan, as shown below.



The next task was to cut a hole in the wallboard and the metal duct behind it for the exhaust fan output.  Unfortunately, our jig saw bumped the ducting askew and it took an hour or so to get it re-aligned and securely taped.  Another hour or so was spent preparing the vent hood for mounting.


The GU10 halogen bulbs for the vent were nearly impossible to get into their sockets, so we had to remove the bottom cover to get a better grip on the bulbs and finally get them in.  I flipped on the circuit breaker and all was well.  I like the 4-speed fan and 3-stage light level.

With the vent installed above the stove area, we moved the stove back into position, hooked up the gas, plugged it in to the AC outlet and fired it up.  No gas leaks and all burners working normally - after we purged the air in the line, that is.

Tonight, I re-installed the door frame that we had removed a couple weeks ago when we re-built and straightened the wall next to the door.  The final wall cabinet will be mounted tomorrow morning after I cut holes for the microwave oven AC outlet and the under-cabinet light.  The base cabinet to the left of the stove is now shimmed level and ready to be secured to the wall.  Then, it's time to assemble our island!

Here's the current state of the installation.

Friday, July 1, 2011

Surprise!

Remember that spacer that we forgot to install yesterday?  Well, today our cabinet supplier stopped by and told us that the "spacer" was actually one of the two spice drawers that we purchased.  So, back out came the sink cabinet and spacer.  Because the water pipes for the sink are surface mounted on the wall behind the cabinets, we had to cut out about 1" of spice rack at the back.  This cutting removed the structural support for one side of the spice rack, so we had to fashion a replacement.  All of this consumed several hours, but it's done and in perfect alignment.  I re-installed the spacer between the lazy susan corner cabinet and the stove.

Spice drawer to the left of the sink & spacer re-installed to left of corner cabinet


Spice drawer pulled out

The decorative face plates for the two spice racks are missing and are now on an expedited order.  Not critical items, in any event.
 
This morning we unpacked the new dishwasher and drilled some holes in the side of the sink cabinet for the water lines.  We'll install the dishwasher in a few days, along with the second spice rack.

We have now finished installing all of the wall cabinets, except for the one with the microwave shelf, which we will install tomorrow, along with the exhaust vent above the stove.  I expect these to take all day, if not longer. 

Here's the current state of the kitchen cabinets:

Thursday, June 30, 2011

Second Base

In preparation for the installation of the corner base cabinet, we installed shims to level our sloping floor.  We have found that masking tape helps to hold the shims in place.





























The corner base cabinet barely fit through the front door, but we removed the cabinet front panels and got it inside.  After tweaking the wall and floor shims, we screwed it to the wall.


Next in line was the sink cabinet, which had to align in three dimensions with the corner cabinet.  The two cabinets were then clamped and screwed together, as illustrated below.
Frames clamped

Pilot holes drilled



Countersink for screw head

Square drive bit and frame screw

Driving in the frame screw

Sink cabinet installation complete


Hey!  What about the spacer?

Spacer? What spacer?

This spacer!
Doh!


So, I uninstalled the cabinet, screwed in the 3" spacer board and reinstalled the cabinet and doors.  Here's the state of things at the end of the day, with the first two base cabinets permanently installed - including the spacer!

Wednesday, June 29, 2011

Cornered

We started unboxing cabinets today and got the first three installed on the corner wall.  The first one went in easier than expected.  Then we remembered that we had forgotten the shims to bring it to a perfect vertical against our perfectly unvertical wall!  So, we backed out the screws, inserted a shim and tightened things back up.



The second cabinet gave us fits, since we had to drill the mounting screws at an angle, which pulled the cabinet out of alignment when tightened.  We finally got it in to our satisfaction, again with a shim between the wall and the back of the cabinet.



By dinner time, we had the third cabinet installed with the doors back on.



We'll install the pull bars later, after more cabinets have been installed.  We did an inventory and appear to be missing some items, such as the panel above the top of the window.  The microwave shelf alignment depends on this panel, so we are holding off on that part of the installation until the missing piece arrives.  Meanwhile, we plan to start installing the lazy susan base cabinet in the corner on Thursday.

Tuesday, June 28, 2011

Refer Madness

In the Navy, we referred to refrigerators as refers.  Seems logical, and it's one of the more benign phrases I learned in the Navy.  In any event, Sears was scheduled to deliver the new fridge between noon and 2pm.  Just before 11am, I got a call from the delivery truck and was informed that they were running "a little ahead of schedule," and would be at our house in 5 minutes!  While Amanda unloaded the refrigerator into our ice chests, I cleared a path through our garage for the delivery crew.  As it turned out, they had to remove our front door and the doors on the new fridge to comfortably maneuver the heavy beast inside.  Amanda was in charge of loading up the new fridge and, as you can see, knew what her #1 priority was.



At first, the refrigerator section would not cool down below the initial 80-degree mark.  Something was wrong.  I was so desperate that I even read the manual.  It appears that the refrigerator went into some sort of safe mode because of the extended time that I had the doors open while removing all the plastic protective sheeting and tape.  A 10-minute power down reset the fridge to normal operation and it finally started to cool down.  Amanda transferred our food from the ice chests and a bunch of microwave meals from the basement freezer to substantially load the thing up.







This evening, I ran a new water line from the basement and through the wall behind the refrigerator for the chilled water dispenser and rolled the refrigerator into its designated position.



























Earlier in the day, I finished drilling and nailing the floor boards along the east wall of the kitchen and out into the hallway by the family room.  Tomorrow, we start installing cabinets in the kitchen!

Drilling the tongue of floorboards near the wall